Mechanics lien law
Alabama lien deadlines for contractors
Updated · Checked against primary sources
The short answer
In Alabama, file a verified lien statement with the probate judge within 6 months after last work or materials if you are the original contractor, 4 months if you are a sub or supplier, and 30 days if you are a journeyman or day laborer. Anyone other than the original contractor must give the owner written notice before filing. Sue within 6 months after the entire debt matures.
The deadlines
| Step | Rule |
|---|---|
| Preliminary notice: who | No statutory preliminary notice for original contractors. Suppliers to a contractor or subcontractor may send an optional pre-furnishing notice of intended materials and prices under 35-11-210; without it their lien is limited to the unpaid balance owed to the contractor. |
| Preliminary notice: when | Optional supplier notice must be given before furnishing the material. Separately, every claimant except the original contractor must give the owner written notice of the lien claim before filing the lien statement (35-11-218). (If the owner objects in writing before the material is used, the full-price lien from the 35-11-210 notice does not apply.) |
| File or register the lien | File the verified statement in the office of the judge of probate of the county: original contractor within 6 months, journeyman and day laborer within 30 days, every other claimant (subs, suppliers) within 4 months, all measured from the last item of work or labor performed or material furnished. |
| Enforce or perfect it | Action to enforce must be commenced within 6 months after the maturity of the entire indebtedness secured by the lien. |
Other notices and rules
- Notice of lien claim (35-11-218): every claimant other than the original contractor must give the owner written notice of the claim, amount, for what and from whom owed, before filing. Not required for material covered by an advance 35-11-210 notice.
- Unpaid balance rule (35-11-210): without the advance supplier notice, a sub or supplier's lien is limited to the unpaid balance the owner owes the contractor.
Common questions
- Do I need to send a preliminary notice in Alabama?
- No statutory preliminary notice for original contractors. Suppliers to a contractor or subcontractor may send an optional pre-furnishing notice of intended materials and prices under 35-11-210; without it their lien is limited to the unpaid balance owed to the contractor. Optional supplier notice must be given before furnishing the material. Separately, every claimant except the original contractor must give the owner written notice of the lien claim before filing the lien statement (35-11-218)..
- How long do I have to file a lien in Alabama?
- File the verified statement in the office of the judge of probate of the county: original contractor within 6 months, journeyman and day laborer within 30 days, every other claimant (subs, suppliers) within 4 months, all measured from the last item of work or labor performed or material furnished.
- How long does a Alabama lien last before I have to enforce it?
- Action to enforce must be commenced within 6 months after the maturity of the entire indebtedness secured by the lien.
General information from the statutes cited below, checked 2026-09-24. Lien law is strict and details depend on your role and contract. Confirm with a construction lawyer in Alabama before relying on a deadline. Read from the 2025 Code of Alabama on Justia. Original contractor period is 6 months, not 4. Section 35-11-218 sets no fixed day count for the pre-filing notice.
Where Pavado comes in
How Pavado builds a CRM around your jobs
Lien rights are usually lost to a calendar, not a court. We build CRMs that start each job's notice and lien clocks from its real start and completion dates and remind you before every deadline, so the rights you earned by doing the work are still there when a customer stops paying.
Instead of bending your shop around someone else's software, we build the system around how your jobs actually move, and connect it to what you already use.
- Your pipeline, your stages. From first call to paid invoice, set up the way your team already works.
- Automations for the busywork. Follow-ups, reminders and handoffs that happen without anyone remembering.
- One record per customer. Calls, quotes, jobs, photos and invoices in one place instead of five apps.
- Connected to your stack. QuickBooks or Xero, Gmail or Outlook, payments and e-sign, plus thousands more through Zapier and an API.
- 1.Book a free demo and walk us through how a job moves today.
- 2.We map the workflow and send a scoped proposal, free.
- 3.We build it, connect your tools and get your team using it.
The first conversation and a scoped proposal are free, and we will tell you early if we are not the right fit.
Go deeper
- GuideWhen to File a Construction Lien: 2026 DeadlinesFile while the clock runs: 30 to 60 days in Canada (60 in Ontario), 90 to 180 in most US states, counted from completion. Registering costs $200 to $500.
- GuideCustomer Short Paid the Final Invoice: 5 MovesBefore you chase the balance, decide whether to deposit the cheque. In the US, cashing one marked 'paid in full' can legally erase what you are owed.
- GuideHow to Collect a Contractor Deposit: 5 RulesMake the deposit due 3 to 5 business days before the start date, size it to your upfront spend, and check state caps: California's is $1,000, not $10,000.
- GuideProgress Payment Schedule: 6 Rules That Get PaidEight states cap what you can collect up front. California's limit is $1,000. How to build a draw schedule under your legal ceiling and stay cash positive.
Other states
- USAlaska lien deadlines
- USArizona lien deadlines
- USArkansas lien deadlines
- USCalifornia lien deadlines
- USColorado lien deadlines
- USConnecticut lien deadlines
Sources
- Ala. Code 35-11-210 (lien declared; supplier notice)
- Ala. Code 35-11-213 (verified statement)
- Ala. Code 35-11-215 (time for filing)
- Ala. Code 35-11-218 (notice by non-original contractors)
- Ala. Code 35-11-221 (limitation of actions)