Mechanics lien law
Wyoming lien deadlines for contractors
Updated · Checked against primary sources
The short answer
In Wyoming, contractors must send the owner a preliminary notice before receiving any payment; subs and suppliers within 30 days after first furnishing. Send a notice of intent at least 20 days before filing. Contractors file within 150 days and others within 120 days of the earlier of last work or substantial completion. Foreclose within 180 days after filing.
The deadlines
| Step | Rule |
|---|---|
| Preliminary notice: who | Contractors, subcontractors and materialmen must all send the record owner or agent written notice of the right to assert a lien; subs and suppliers also copy the contractor they work for (W.S. 29-2-112(a)(i)). Missing the deadline bars the lien. |
| Preliminary notice: when | Contractor: before receiving any payment from the owner, including advances. Subcontractor or materialman: within 30 days after first providing services or materials. |
| File or register the lien | Contractors file the lien statement within 150 days, and all others within 120 days, of the earlier of the last day work was performed or materials furnished under the contract, or substantial completion of the project; for a subcontractor, after the last day it worked at the contractor's direction (W.S. 29-2-106(a)). A recorded notice of substantial completion is presumed to set that date. Send the owner a notice of intent to file at least 20 days before filing (29-2-107). |
| Enforce or perfect it | Commence an action to foreclose within 180 days after filing the lien statement (W.S. 29-2-109). |
Common questions
- Do I need to send a preliminary notice in Wyoming?
- Contractors, subcontractors and materialmen must all send the record owner or agent written notice of the right to assert a lien; subs and suppliers also copy the contractor they work for (W.S. 29-2-112(a)(i)). Missing the deadline bars the lien. Contractor: before receiving any payment from the owner, including advances. Subcontractor or materialman: within 30 days after first providing services or materials..
- How long do I have to file a lien in Wyoming?
- Contractors file the lien statement within 150 days, and all others within 120 days, of the earlier of the last day work was performed or materials furnished under the contract, or substantial completion of the project; for a subcontractor, after the last day it worked at the contractor's direction (W.S. 29-2-106(a)). A recorded notice of substantial completion is presumed to set that date. Send the owner a notice of intent to file at least 20 days before filing (29-2-107).
- How long does a Wyoming lien last before I have to enforce it?
- Commence an action to foreclose within 180 days after filing the lien statement (W.S. 29-2-109).
General information from the statutes cited below, checked 2026-09-24. Lien law is strict and details depend on your role and contract. Confirm with a construction lawyer in Wyoming before relying on a deadline.
Where Pavado comes in
How Pavado builds a CRM around your jobs
Lien rights are usually lost to a calendar, not a court. We build CRMs that start each job's notice and lien clocks from its real start and completion dates and remind you before every deadline, so the rights you earned by doing the work are still there when a customer stops paying.
Instead of bending your shop around someone else's software, we build the system around how your jobs actually move, and connect it to what you already use.
- Your pipeline, your stages. From first call to paid invoice, set up the way your team already works.
- Automations for the busywork. Follow-ups, reminders and handoffs that happen without anyone remembering.
- One record per customer. Calls, quotes, jobs, photos and invoices in one place instead of five apps.
- Connected to your stack. QuickBooks or Xero, Gmail or Outlook, payments and e-sign, plus thousands more through Zapier and an API.
- 1.Book a free demo and walk us through how a job moves today.
- 2.We map the workflow and send a scoped proposal, free.
- 3.We build it, connect your tools and get your team using it.
The first conversation and a scoped proposal are free, and we will tell you early if we are not the right fit.
Go deeper
- GuideWhen to File a Construction Lien: 2026 DeadlinesFile while the clock runs: 30 to 60 days in Canada (60 in Ontario), 90 to 180 in most US states, counted from completion. Registering costs $200 to $500.
- GuideCustomer Short Paid the Final Invoice: 5 MovesBefore you chase the balance, decide whether to deposit the cheque. In the US, cashing one marked 'paid in full' can legally erase what you are owed.
- GuideHow to Collect a Contractor Deposit: 5 RulesMake the deposit due 3 to 5 business days before the start date, size it to your upfront spend, and check state caps: California's is $1,000, not $10,000.
- GuideProgress Payment Schedule: 6 Rules That Get PaidEight states cap what you can collect up front. California's limit is $1,000. How to build a draw schedule under your legal ceiling and stay cash positive.
Other states
- USAlabama lien deadlines
- USAlaska lien deadlines
- USArizona lien deadlines
- USArkansas lien deadlines
- USCalifornia lien deadlines
- USColorado lien deadlines
Sources
Cite this page
Pavado, “Wyoming Lien Deadlines 2026: Notice and Filing”, https://www.pavadotech.com/lien-deadlines/wyoming, updated 2026-09-24.